During the first phase, we added 2 MW of critical capacity and 12,000 sq ft of white space adjacent to the existing data center. In addition to the new data center expansion, we also remodeled offices, built an equipment yard, and expanded existing meet-me rooms. The second phase involved the selective demolition of an existing warehouse space within the active data center facility, followed by the build-out of approximately 80,000 sq ft of interior space and an additional 30,000 sq ft of an exterior equipment yard. This expansion was designed to support three data halls, each providing 12,000 sq ft of white space, for a total server capacity of 8 MW. The facility is designed to meet Tier III standards with a density of 100 W per sq ft and N+1 redundancy to ensure reliable and continuous operation of critical systems.

Client

Confidential

Project Stats

132,700 sq ft